Tutor Perini Reports Third Quarter 2022 Results
LOS ANGELES--(BUSINESS WIRE)--Nov 2, 2022--
Tutor Perini Corporation (the “Company”) (NYSE: TPC), a leading civil, building and specialty construction company, reported results today for the third quarter of 2022. Revenue was $1.1 billion compared to $1.2 billion for the third quarter of last year. The decrease was primarily due to reduced project execution activities on various projects in all three segments. Loss from construction operations for the third quarter of 2022 was $6.9 million, compared to income from construction operations of $52.1 million for the same period in 2021. The decrease was largely due to reduced project execution activities on a transportation project in the Northeast that is nearing completion, which impacted all three segments, as well as unfavorable adjustments that resulted from two adverse legal rulings, one of which reversed a previously favorable lower-court ruling. As a result, net loss attributable to the Company for the third quarter of 2022 was $32.5 million, or a $0.63 loss per diluted share, compared to net income attributable to the Company of $15.4 million, or $0.30 of earnings per diluted share, for the third quarter of 2021.
The Company generated $72.6 million and $251.3 million of cash from operating activities in the third quarter and first nine months of 2022, respectively, compared to usage of $21.3 million and $152.6 million for the same periods of 2021. The result for the third quarter of 2022 was one of the largest operating cash results of any third quarter since the 2008 merger between Tutor-Saliba Corporation and Perini Corporation, and was an increase of $93.9 million compared to the operating cash usage of $21.3 million in the third quarter of 2021. The Company anticipates continued operating cash generation for the fourth quarter of 2022, as well as strong operating cash generation in 2023.
Backlog was $8.4 billion as of September 30, 2022, level compared to the same period last year. The most significant new awards and contract adjustments in the third quarter of 2022 included $142 million of additional funding for two educational facility projects in California; a $126 million military facilities project in Puerto Rico; $56 million of additional funding for a mass-transit project in the Midwest; a $48 million mining project in Virginia; and a $32 million hospitality project in California. The Company has recently bid and is preparing to bid various large projects, with awards anticipated later this year and next year. In addition, the Company recently announced two significant new projects — the Raritan River Bridge Replacement project in New Jersey and Phase 1 South of the New American Legion Bridge I-270 Traffic Relief Plan in Maryland — with contract awards pending over the next three to six months of a combined value that could exceed $4.5 billion. The Company also expects that substantial incremental federal funding to be provided under the Infrastructure Investment and Jobs Act (also known as the Bipartisan Infrastructure Law) over the next several years will favorably impact the Company's current work and prospective opportunities.
Outlook and Guidance
“We generated strong operating cash in the third quarter of 2022, setting a new record operating cash result for the first nine months of any year since 2008, and expect that operating cash will be continue to be solid for the rest of this year and in 2023,” said Ronald Tutor, Chairman and Chief Executive Officer. Tutor continued, “Our backlog remains healthy at $8.4 billion, and we look forward to adding several significant new contract awards over the coming months, which should position our backlog at a new all-time high and provide a strong foundation for growth and improved profitability over the next several years. Our civil business, from which we derive the majority of our profit, is highly resilient to economic downturns, and our bidding pipeline continues to be very robust and is expected to further expand as substantial incremental funds from the Bipartisan Infrastructure Law flow to our customers to support many existing and future projects. Although we were disappointed with our third-quarter earnings, we remain encouraged by the progress we are continuing to make in resolving disputed matters and collecting significant amounts of associated cash.”
Debt reduction remains the Company's primary near-term focus for its use of cash. In accordance with the requirements of its debt agreements, on or before April 7, 2023, the Company currently expects to make an excess cash paydown of approximately $100 million on the outstanding balance of its Term Loan B. Depending on conditions after the Term Loan B paydown is completed, and in light of various factors, including the Company's record operating cash generation to date in 2022, solid cash generation that is expected to continue throughout next year, the Company's current and expected larger future backlog, and substantial anticipated funding over the next several years from the Bipartisan Infrastructure Law, the Company may then consider additional capital optimization strategies.
Third Quarter 2022 Conference Call
The Company will host a conference call at 2:00 PM Pacific Time on Wednesday, November 2, 2022, to discuss the third quarter 2022 results. To participate in the conference call, please dial 877-407-8293 five to ten minutes prior to the scheduled time. International callers should dial 1-201-689-8349.
The conference call will be webcast live over the Internet and can be accessed by all interested parties on Tutor Perini's website at www.tutorperini.com. For those unable to participate during the live call, the webcast will be available for replay shortly after the call on the website.
About Tutor Perini Corporation
Tutor Perini Corporation is a leading civil, building and specialty construction company offering diversified general contracting and design-build services to private customers and public agencies throughout the world. We have provided construction services since 1894 and have established a strong reputation within our markets by executing large, complex projects on time and within budget, while adhering to strict quality control measures. We offer general contracting, pre-construction planning and comprehensive project management services, including planning and scheduling of manpower, equipment, materials and subcontractors required for a project. We also offer self-performed construction services including site work, concrete forming and placement, steel erection, electrical, mechanical, plumbing and heating, ventilation and air conditioning (HVAC). We are known for our major complex building project commitments, as well as our capacity to perform large and complex transportation and heavy civil construction for government agencies and private customers throughout the world.
Forward-Looking Statements
The statements contained in this release, including those set forth in the section “Outlook and Guidance,” that are not purely historical are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended, including without limitation, statementsregarding the Company’s expectations, hopes, beliefs, intentions or strategies regarding the future and statements regarding future guidance or estimates and non-historical performance. These forward-looking statements are based on the Company’s current expectations and beliefs concerning future developments and their potential effects on the Company. While the Company’s expectations, beliefs and projections are expressed in good faith and the Company believes there is a reasonable basis for them, there can be no assurance that future developments affecting the Company will be those that we have anticipated. These forward-looking statements involve a number of risks, uncertainties (some of which are beyond the control of the Company) or other assumptions that may cause actual results or performance to be materially different from those expressed or implied by such forward-looking statements. These risks and uncertainties include, but are not limited to: revisions of estimates of contract risks, revenue or costs, economic factors such as inflation or a recession, the timing of new awards, or the pace of project execution, which has resulted and may continue to result in losses or lower than anticipated profit; unfavorable outcomes of existing or future litigation or dispute resolution proceedings against us or customers (project owners, developers, general contractors, etc.), subcontractors or suppliers, as well as failure to promptly recover significant working capital invested in projects subject to such matters; a significant slowdown or decline in economic conditions; increased competition and failure to secure new contracts; contract requirements to perform extra work beyond the initial project scope, which has and in the future could result in disputes or claims and adversely affect our working capital, profits and cash flows; risks and other uncertainties associated with assumptions and estimates used to prepare our financial statements; failure to meet contractual schedule requirements, which could result in higher costs and reduced profits or, in some cases, exposure to financial liability for liquidated damages and/or damages to customers, as well as damage to our reputation; inability to attract and retain our key officers, and to adequately plan for their succession, and hire and retain personnel required to execute and perform on our contracts; risks related to our international operations, such as uncertainty of U.S. Government funding, as well as economic, political, regulatory and other risks, including risks of loss due to acts of war, civil unrest, security issues, labor conditions, corruption and other unforeseeable events in countries where we do business, resulting in unanticipated losses; possible systems and information technology interruptions and breaches in data security and/or privacy; client cancellations of, or reductions in scope under, contracts reported in our backlog; securities litigation and/or shareholder activism; failure of our joint venture partners to perform their venture obligations, which could impose additional financial and performance obligations on us, resulting in reduced profits or losses and/or reputational harm; downgrades in our credit ratings; the impact of inclement weather conditions on projects; decreases in the level of government spending for infrastructure and other public projects; risks related to government contracts and related procurement regulations; failure to meet our obligations under our debt agreements; the COVID-19 pandemic, which has adversely impacted, and could continue to adversely impact, our business, financial condition and results of operations by, among other things, delaying the timing of project bids and/or awards and the timing of dispute resolutions and associated collections; violations of the U.S. Foreign Corrupt Practices Act and similar worldwide anti-bribery laws; adverse health events, such as an epidemic or another pandemic; physical and regulatory risks related to climate change; impairment of our goodwill or other indefinite-lived intangible assets; the exertion of influence over the Company by our chairman and chief executive officer due to his position and significant ownership interest; and other risks and uncertainties discussed under the heading “Risk Factors” in our Annual Report on Form 10-K for the year ended December 31, 2021 filed on February 24, 2022 and in other reports that we file with the Securities and Exchange Commission from time to time. The Company undertakes no obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as may be required under applicable securities laws.
Tutor Perini Corporation | ||||||||||||||||
Condensed Consolidated Statements of Operations | ||||||||||||||||
Unaudited | ||||||||||||||||
|
|
|
|
|
|
|
|
| ||||||||
|
| Three Months Ended September 30, |
| Nine Months Ended September 30, | ||||||||||||
(in thousands, except per common share amounts) |
| 2022 |
| 2021 |
| 2022 |
| 2021 | ||||||||
REVENUE |
| $ | 1,070,926 |
|
| $ | 1,178,222 |
|
| $ | 2,884,107 |
|
| $ | 3,605,060 |
|
COST OF OPERATIONS |
|
| (1,020,586 | ) |
|
| (1,064,245 | ) |
|
| (2,817,645 | ) |
|
| (3,253,139 | ) |
GROSS PROFIT |
|
| 50,340 |
|
|
| 113,977 |
|
|
| 66,462 |
|
|
| 351,921 |
|
General and administrative expenses |
|
| (57,232 | ) |
|
| (61,884 | ) |
|
| (173,815 | ) |
|
| (181,371 | ) |
INCOME (LOSS) FROM CONSTRUCTION OPERATIONS |
|
| (6,892 | ) |
|
| 52,093 |
|
|
| (107,353 | ) |
|
| 170,550 |
|
Other income (expense) |
|
| 397 |
|
|
| (464 | ) |
|
| 5,114 |
|
|
| 1,142 |
|
Interest expense |
|
| (17,015 | ) |
|
| (16,694 | ) |
|
| (49,711 | ) |
|
| (52,442 | ) |
INCOME (LOSS) BEFORE INCOME TAXES |
|
| (23,510 | ) |
|
| 34,935 |
|
|
| (151,950 | ) |
|
| 119,250 |
|
Income tax (expense) benefit |
|
| (560 | ) |
|
| (8,694 | ) |
|
| 47,047 |
|
|
| (26,293 | ) |
NET INCOME (LOSS) |
|
| (24,070 | ) |
|
| 26,241 |
|
|
| (104,903 | ) |
|
| 92,957 |
|
LESS: NET INCOME ATTRIBUTABLE TO NONCONTROLLING INTERESTS |
|
| 8,385 |
|
|
| 10,847 |
|
|
| 12,189 |
|
|
| 30,364 |
|
NET INCOME (LOSS) ATTRIBUTABLE TO TUTOR PERINI CORPORATION |
| $ | (32,455 | ) |
| $ | 15,394 |
|
| $ | (117,092 | ) |
| $ | 62,593 |
|
BASIC EARNINGS (LOSS) PER COMMON SHARE |
| $ | (0.63 | ) |
| $ | 0.30 |
|
| $ | (2.28 | ) |
| $ | 1.23 |
|
DILUTED EARNINGS (LOSS) PER COMMON SHARE |
| $ | (0.63 | ) |
| $ | 0.30 |
|
| $ | (2.28 | ) |
| $ | 1.22 |
|
WEIGHTED-AVERAGE COMMON SHARES OUTSTANDING: |
|
|
|
|
|
|
|
| ||||||||
BASIC |
|
| 51,404 |
|
|
| 51,072 |
|
|
| 51,263 |
|
|
| 50,995 |
|
DILUTED |
|
| 51,404 |
|
|
| 51,366 |
|
|
| 51,263 |
|
|
| 51,364 |
|
Tutor Perini Corporation | ||||||||||||||||||||
Segment Information | ||||||||||||||||||||
Unaudited | ||||||||||||||||||||
|
|
|
|
|
|
|
|
| ||||||||||||
Reportable Segments |
|
|
|
| ||||||||||||||||
(in thousands) | Civil | Building | Specialty Contractors | Total |
| Corporate |
| Consolidated Total | ||||||||||||
Three Months Ended September 30, 2022 | ||||||||||||||||||||
Total revenue | $ | 564,205 |
| $ | 341,614 |
| $ | 251,974 |
| $ | 1,157,793 |
|
| $ | — |
|
| $ | 1,157,793 |
|
Elimination of intersegment revenue |
| (63,300 | ) |
| (23,564 | ) |
| (3 | ) |
| (86,867 | ) |
|
| — |
|
|
| (86,867 | ) |
Revenue from external customers | $ | 500,905 |
| $ | 318,050 |
| $ | 251,971 |
| $ | 1,070,926 |
|
| $ | — |
|
| $ | 1,070,926 |
|
Income (loss) from construction operations | $ | 22,786 |
| $ | 56 |
| $ | (11,836 | ) | $ | 11,006 | (a) |
| $ | (17,898 | ) (b) | $ | (6,892 | ) | |
Capital expenditures | $ | 11,872 |
| $ | 921 |
| $ | 748 |
| $ | 13,541 |
|
| $ | 423 |
|
| $ | 13,964 |
|
Depreciation and amortization (c) | $ | 12,166 |
| $ | 470 |
| $ | 529 |
| $ | 13,165 |
|
| $ | 2,368 |
|
| $ | 15,533 |
|
|
|
|
|
|
|
|
|
| ||||||||||||
Three Months Ended September 30, 2021 | ||||||||||||||||||||
Total revenue | $ | 624,549 |
| $ | 395,013 |
| $ | 271,316 |
| $ | 1,290,878 |
|
| $ | — |
|
| $ | 1,290,878 |
|
Elimination of intersegment revenue |
| (78,331 | ) |
| (34,072 | ) |
| (253 | ) |
| (112,656 | ) |
|
| — |
|
|
| (112,656 | ) |
Revenue from external customers | $ | 546,218 |
| $ | 360,941 |
| $ | 271,063 |
| $ | 1,178,222 |
|
| $ | — |
|
| $ | 1,178,222 |
|
Income (loss) from construction operations | $ | 62,555 |
| $ | 10,786 |
| $ | (5,470 | ) | $ | 67,871 |
|
| $ | (15,778 | ) (b) |
| $ | 52,093 |
|
Capital expenditures | $ | 7,847 |
| $ | 87 |
| $ | 134 |
| $ | 8,068 |
|
| $ | 234 |
|
| $ | 8,302 |
|
Depreciation and amortization (c) | $ | 26,234 |
| $ | 416 |
| $ | 777 |
| $ | 27,427 |
|
| $ | 2,634 |
|
| $ | 30,061 |
|
(a) |
| During the three months ended September 30, 2022, the Company’s income (loss) from construction operations was adversely impacted by a $14.3 million ($10.2 million, or $0.20 per diluted share, after tax) unfavorable adjustment on a completed Civil segment highway project in the Northeast due to the reversal on appeal of a previously favorable lower-court ruling. |
(b) |
| Consists primarily of corporate general and administrative expenses. |
(c) |
| Depreciation and amortization is included in income (loss) from construction operations. |
Reportable Segments |
|
|
|
| ||||||||||||||||
(in thousands) | Civil | Building | Specialty Contractors | Total |
| Corporate |
| Consolidated Total | ||||||||||||
Nine Months Ended September 30, 2022 | ||||||||||||||||||||
Total revenue | $ | 1,478,162 |
| $ | 960,148 |
| $ | 673,302 |
| $ | 3,111,612 |
|
| $ | — |
|
| $ | 3,111,612 |
|
Elimination of intersegment revenue |
| (182,840 | ) |
| (44,509 | ) |
| (156 | ) |
| (227,505 | ) |
|
| — |
|
|
| (227,505 | ) |
Revenue from external customers | $ | 1,295,322 |
| $ | 915,639 |
| $ | 673,146 |
| $ | 2,884,107 |
|
| $ | — |
|
| $ | 2,884,107 |
|
Income (loss) from construction operations | $ | 12,052 |
| $ | 9,453 |
| $ | (82,461 | ) | $ | (60,956 | ) (a) |
| $ | (46,397 | ) (b) |
| $ | (107,353 | ) |
Capital expenditures | $ | 38,703 |
| $ | 973 |
| $ | 2,202 |
| $ | 41,878 |
|
| $ | 931 |
|
| $ | 42,809 |
|
Depreciation and amortization (c) | $ | 44,191 |
| $ | 1,261 |
| $ | 1,539 |
| $ | 46,991 |
|
| $ | 7,063 |
|
| $ | 54,054 |
|
|
|
|
|
|
|
|
|
| ||||||||||||
Nine Months Ended September 30, 2021 | ||||||||||||||||||||
Total revenue | $ | 1,850,748 |
| $ | 1,267,984 |
| $ | 877,634 |
| $ | 3,996,366 |
|
| $ | — |
|
| $ | 3,996,366 |
|
Elimination of intersegment revenue |
| (273,603 | ) |
| (117,150 | ) |
| (553 | ) |
| (391,306 | ) |
|
| — |
|
|
| (391,306 | ) |
Revenue from external customers | $ | 1,577,145 |
| $ | 1,150,834 |
| $ | 877,081 |
| $ | 3,605,060 |
|
| $ | — |
|
| $ | 3,605,060 |
|
Income (loss) from construction operations | $ | 187,733 |
| $ | 19,514 |
| $ | 5,814 |
| $ | 213,061 | (d) |
| $ | (42,511 | ) (b) |
| $ | 170,550 |
|
Capital expenditures | $ | 26,027 |
| $ | 211 |
| $ | 298 |
| $ | 26,536 |
|
| $ | 626 |
|
| $ | 27,162 |
|
Depreciation and amortization (c) | $ | 80,125 |
| $ | 1,272 |
| $ | 2,628 |
| $ | 84,025 |
|
| $ | 8,171 |
|
| $ | 92,196 |
|
(a) |
| During the nine months ended September 30, 2022, the Company’s income (loss) from construction operations was adversely impacted by $36.0 million ($26.0 million, or $0.51 per diluted share, after tax) due to unfavorable adjustments related to the unforeseen cost of project close-out issues, remediation work, extended project supervision and associated labor inefficiencies on the electrical component of a transportation project in the Northeast in the Specialty Contractors segment, and $34.6 million ($27.3 million, or $0.53 per diluted share, after tax) for a Civil segment mass-transit project in California, which resulted from the successful negotiation of significant lower margin (and lower risk) change orders that increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage. The Company’s income (loss) from construction operations was also impacted by a non-cash charge of $25.5 million ($18.3 million, or $0.36 per diluted share, after tax) due to an adverse legal ruling on a dispute related to a completed Civil segment bridge project in New York, an $18.0 million ($13.9 million, or $0.27 per diluted share, after tax) unfavorable adjustment split evenly between the Civil and Building segments due to changes in estimates on the same transportation project in the Northeast mentioned above, a non-cash charge of $17.8 million ($12.8 million, or $0.25 per diluted share, after tax) that increased cost of operations associated with the partial reversal by an appellate court of previously awarded legal damages related to a completed electrical project in New York in the Specialty Contractors segment, a $16.2 million ($11.6 million, or $0.23 per diluted share, after tax) unfavorable non-cash impact related to the settlement of a long-disputed, completed Civil segment project in Maryland, a $14.3 million ($10.2 million, or $0.20 per diluted share, after tax) unfavorable adjustment on a completed Civil segment highway project in the Northeast due to the reversal on appeal of a previously favorable lower-court ruling, and $13.1 million ($9.4 million, or $0.18 per diluted share, after tax) of unfavorable adjustments on a Civil segment mass-transit project in California. |
(b) |
| Consists primarily of corporate general and administrative expenses. |
(c) |
| Depreciation and amortization is included in income (loss) from construction operations. |
(d) |
| During the nine months ended September 30, 2021, the Company recorded a reduction of $20.1 million in cost of operations ($14.6 million, or $0.28 per diluted share, after tax) due to a favorable trial court ruling awarding the Company the recovery of certain costs previously incurred on a completed electrical project in New York in the Specialty Contractors segment. The Company also recognized $18.1 million of additional revenue ($13.0 million, or $0.25 per diluted share, after tax) as a result of favorable adjustments on a Civil segment mass-transit project in California reflecting improved profitability due to the mitigation of certain risks as the project progresses toward completion. The Company’s income from construction operations was also negatively impacted by $14.5 million ($10.5 million, or $0.21 per diluted share, after-tax) due to changes in estimates on an electrical project in New York in the Specialty Contractors segment that included unfavorable adjustments and the negative impact to the period associated with increases to project forecasts due to growth in unapproved change orders (expected to be negotiated in future periods). |
Tutor Perini Corporation | ||||||||
Condensed Consolidated Balance Sheets | ||||||||
Unaudited | ||||||||
(in thousands, except share and per share amounts) |
| As of September 30, 2022 |
| As of December 31, 2021 | ||||
ASSETS | ||||||||
CURRENT ASSETS: |
|
|
|
| ||||
Cash and cash equivalents ($158,943 and $102,679 related to variable interest entities (“VIEs”)) |
| $ | 323,200 |
| $ | 202,197 | ||
Restricted cash |
|
| 21,817 |
|
|
| 9,199 |
|
Restricted investments |
|
| 79,562 |
|
|
| 84,355 |
|
Accounts receivable ($65,059 and $116,415 related to VIEs) |
|
| 1,252,943 |
|
|
| 1,454,319 |
|
Retention receivable ($184,797 and $162,259 related to VIEs) |
|
| 583,789 |
|
|
| 568,881 |
|
Costs and estimated earnings in excess of billings ($97,510 and $143,105 related to VIEs) |
|
| 1,448,341 |
|
|
| 1,356,768 |
|
Other current assets ($37,816 and $43,718 related to VIEs) |
|
| 196,401 |
|
|
| 186,773 |
|
Total current assets |
|
| 3,906,053 |
|
|
| 3,862,492 |
|
PROPERTY AND EQUIPMENT ("P&E"), net of accumulated depreciation of $500,692 and $483,417 (net P&E of $16,016 and $2,203 related to VIEs) |
|
| 429,911 |
|
|
| 429,645 |
|
GOODWILL |
|
| 205,143 |
|
|
| 205,143 |
|
INTANGIBLE ASSETS, NET |
|
| 71,102 |
|
|
| 85,068 |
|
OTHER ASSETS |
|
| 148,765 |
|
|
| 142,550 |
|
TOTAL ASSETS |
| $ | 4,760,974 |
|
| $ | 4,724,898 |
|
LIABILITIES AND EQUITY | ||||||||
CURRENT LIABILITIES: |
|
|
|
| ||||
Current maturities of long-term debt |
| $ | 26,875 |
|
| $ | 24,406 |
|
Accounts payable ($62,943 and $96,097 related to VIEs) |
|
| 589,689 |
|
|
| 512,056 |
|
Retention payable ($43,174 and $37,007 related to VIEs) |
|
| 241,518 |
|
|
| 268,945 |
|
Billings in excess of costs and estimated earnings ($468,130 and $355,270 related to VIEs) |
|
| 966,065 |
|
|
| 761,689 |
|
Accrued expenses and other current liabilities ($10,675 and $8,566 related to VIEs) |
|
| 216,922 |
|
|
| 210,017 |
|
Total current liabilities |
|
| 2,041,069 |
|
|
| 1,777,113 |
|
LONG-TERM DEBT, less current maturities, net of unamortized discount and debt issuance costs totaling $14,784 and $17,109 |
|
| 934,259 |
|
|
| 969,248 |
|
DEFERRED INCOME TAXES |
|
| 13,760 |
|
|
| 70,989 |
|
OTHER LONG-TERM LIABILITIES |
|
| 252,523 |
|
|
| 233,828 |
|
TOTAL LIABILITIES |
|
| 3,241,611 |
|
|
| 3,051,178 |
|
COMMITMENTS AND CONTINGENCIES |
|
|
|
| ||||
EQUITY |
|
|
|
| ||||
Stockholders' equity: |
|
|
|
| ||||
Preferred stock - authorized 1,000,000 shares ($1 par value), none issued |
|
| — |
|
|
| — |
|
Common stock - authorized 112,500,000 shares ($1 par value), issued and outstanding 51,485,216 and 51,095,706 shares |
|
| 51,485 |
|
|
| 51,096 |
|
Additional paid-in capital |
|
| 1,139,905 |
|
|
| 1,133,150 |
|
Retained earnings |
|
| 397,218 |
|
|
| 514,310 |
|
Accumulated other comprehensive loss |
|
| (52,017 | ) |
|
| (43,635 | ) |
Total stockholders' equity |
|
| 1,536,591 |
|
|
| 1,654,921 |
|
Noncontrolling interests |
|
| (17,228 | ) |
|
| 18,799 |
|
TOTAL EQUITY |
|
| 1,519,363 |
|
|
| 1,673,720 |
|
TOTAL LIABILITIES AND EQUITY |
| $ | 4,760,974 |
|
| $ | 4,724,898 |
|
Tutor Perini Corporation | |||||||
Condensed Consolidated Statements of Cash Flows | |||||||
Unaudited | |||||||
Nine Months Ended September 30, | |||||||
(in thousands) | 2022 |
| 2021 | ||||
Cash Flows from Operating Activities: |
|
|
| ||||
Net income (loss) | $ | (104,903 | ) |
| $ | 92,957 |
|
Adjustments to reconcile net income (loss) to net cash provided by (used in) operating activities: |
|
|
| ||||
Depreciation |
| 40,088 |
|
|
| 65,550 |
|
Amortization of intangible assets |
| 13,966 |
|
|
| 26,646 |
|
Share-based compensation expense |
| 7,681 |
|
|
| 8,103 |
|
Change in debt discounts and deferred debt issuance costs |
| 2,751 |
|
|
| 4,802 |
|
Deferred income taxes |
| (53,365 | ) |
|
| 124 |
|
(Gain) loss on sale of property and equipment |
| (183 | ) |
|
| 2,004 |
|
Changes in other components of working capital |
| 338,527 |
|
|
| (363,074 | ) |
Other long-term liabilities |
| 10,862 |
|
|
| 11,225 |
|
Other, net |
| (4,146 | ) |
|
| (955 | ) |
NET CASH PROVIDED BY (USED IN) OPERATING ACTIVITIES |
| 251,278 |
|
|
| (152,618 | ) |
|
|
| |||||
Cash Flows from Investing Activities: |
|
|
| ||||
Acquisition of property and equipment |
| (42,809 | ) |
|
| (27,162 | ) |
Proceeds from sale of property and equipment |
| 6,738 |
|
|
| 5,236 |
|
Investments in securities |
| (11,145 | ) |
|
| (25,541 | ) |
Proceeds from maturities and sales of investments in securities |
| 8,333 |
|
|
| 16,443 |
|
NET CASH USED IN INVESTING ACTIVITIES |
| (38,883 | ) |
|
| (31,024 | ) |
|
|
| |||||
Cash Flows from Financing Activities: |
|
|
| ||||
Proceeds from debt |
| 498,606 |
|
|
| 448,270 |
|
Repayment of debt |
| (533,452 | ) |
|
| (510,146 | ) |
Cash payments related to share-based compensation |
| (1,389 | ) |
|
| (1,627 | ) |
Distributions paid to noncontrolling interests |
| (46,500 | ) |
|
| (17,250 | ) |
Contributions from noncontrolling interests |
| 3,961 |
|
|
| 7,000 |
|
NET CASH USED IN FINANCING ACTIVITIES |
| (78,774 | ) |
|
| (73,753 | ) |
|
|
| |||||
Net increase (decrease) in cash, cash equivalents and restricted cash |
| 133,621 |
|
|
| (257,395 | ) |
Cash, cash equivalents and restricted cash at beginning of period |
| 211,396 |
|
|
| 451,852 |
|
Cash, cash equivalents and restricted cash at end of period | $ | 345,017 |
|
| $ | 194,457 |
|
Tutor Perini Corporation | ||||||||||||||||
Backlog Information | ||||||||||||||||
Unaudited | ||||||||||||||||
(in millions) |
| Backlog at |
| New Awards in the |
| Revenue Recognized |
| Backlog at | ||||||||
Civil |
| $ | 4,926.6 |
| $ | 225.1 |
| $ | (500.9 | ) |
| $ | 4,650.8 | |||
Building |
|
| 2,243.2 |
|
|
| 415.9 |
|
|
| (318.0 | ) |
|
| 2,341.1 |
|
Specialty Contractors |
|
| 1,366.3 |
|
|
| 244.1 |
|
|
| (252.0 | ) |
|
| 1,358.4 |
|
Total |
| $ | 8,536.1 |
|
| $ | 885.1 |
|
| $ | (1,070.9 | ) |
| $ | 8,350.3 |
|
(in millions) |
| Backlog at |
| New Awards in the |
| Revenue Recognized |
| Backlog at | ||||||||
Civil |
| $ | 4,553.5 |
| $ | 1,392.6 |
| $ | (1,295.3 | ) |
| $ | 4,650.8 | |||
Building |
|
| 2,308.9 |
|
|
| 947.8 |
|
|
| (915.6 | ) |
|
| 2,341.1 |
|
Specialty Contractors |
|
| 1,373.2 |
|
|
| 658.4 |
|
|
| (673.2 | ) |
|
| 1,358.4 |
|
Total |
| $ | 8,235.6 |
|
| $ | 2,998.8 |
|
| $ | (2,884.1 | ) |
| $ | 8,350.3 |
|
(a) |
| New awards consist of the original contract price of projects added to our backlog plus or minus subsequent changes to the estimated total contract price of existing contracts. |
View source version on businesswire.com:https://www.businesswire.com/news/home/20221102005332/en/
CONTACT: Tutor Perini Corporation
Jorge Casado, 818-362-8391
Vice President, Investor Relations & Corporate Communications
www.tutorperini.com
KEYWORD: CALIFORNIA UNITED STATES NORTH AMERICA
INDUSTRY KEYWORD: ARCHITECTURE COMMERCIAL BUILDING & REAL ESTATE CONSTRUCTION & PROPERTY BUILDING SYSTEMS ENGINEERING URBAN PLANNING OTHER CONSTRUCTION & PROPERTY MANUFACTURING
SOURCE: Tutor Perini Corporation
Copyright Business Wire 2022.